arrow_backTo the overview16 June 2025 | Bredenoord
Construction firm Heijmans came to Bredenoord with a specific query. They had an upcoming project in Amersfoort that involved drilling under the train tracks. However, there was no grid access on location, so Heijmans was looking for a mobile power supply. Their contractor had an additional demand though: the drilling had to be executed emission-free. Bredenoord then came up with a fitting solution: using a Battery Box 300L, which would power Heijmans’ electric power pack.
The Battery Box 300L is turned off at night, but since they want to power a camera then we also set up a smaller battery: the Battery Box 30. This is also connected to the crew wagon, to power devices such as the coffee machine.
This setup allows Heijmans to work for an entire week without an on-site grid connection and without having to set up a genset